Project CPI and SPI

Make sure following have been done, otherwise they will stay zero “0”.

  • Status Date is set to NA or set appropriately. (Can only be done from MS Project)
  • Project is baselined
  • Some progress has been applied “PercentageComplete”
  • Cost have been set

 